Mission SSC CGL 2016 – Quiz – Day 11 – Maths


Hello and welcome to exampundit . Here is the 11th Quiz of the 50 Days Mission SSC CGL 2016 series.

1. P and Q together can do a job in 6 days.  Q and R can do the same job in 60/7 days.  P wored for 3 days after starting it.  Q and R worked for 6 days. The difference in days in which R and B can complete the job is ?
1.  10
2.  15
3.  3
4.  8


2. A road of 5km length will be constructed in 100 days.  So 280 workers were employed.  But after 80 days only 3 ½ km road was completed. How many more people are needed to finish the work in specified time?
1.  280
2.  200
3.  220
4.  500


3.  A train passes 2 bridges of lengths 800 m and 400 m in 100 and 60 seconds respectively. The length of the train is :
1.  80
2.  90
3.  200
4.  24


4. If a distance of 50 m is covered in 1 minute, 90 m in 2 minutes and 130 m in 3 minutes. Find the distance (in m) covered in 15 minutes.
1.  750
2.  1000
3.  650
4.  610


5. A train leaves a station A at 7 am and reaches B at 11 am.  Another train leaves B at 8 am and reaches A at 11 30 am. The two trains cross each other at ?
1.  9. 24 am
2.  9. 24pm
3.  8. 56am
4.  9. 00am


6. If a boy walks from his house to school @ 4kmph, he reaches school 10 minutes earlier. If he walks @ 3kmph, he reaches 10 minutes late.  Find the distance from home to school?
1.  2 km
2.  4km
3.  5 km
4.  4. 6 km


7. Speed of motorboat in still water is 45 kmph. If the motorboat travels 80 km along the stream in 1 hour 20 minutes, then the time taken by it to cover the same distance against the stream will be
1.  3 hours
2.  1 hr 20 mins
3.  2 hr 40 mins
4.  2 hr 55 mins



8. the ratio of speed of motorboat to that of current water is 36:5. The boat goes along the current in 5 hrs 10 mins. It will come back in ?
1.  5 hrs 50 mins
2.  4 hrs 30 mins
3.  5 hrs 30 mins
4.  6 hrs 50 mins


9. A tank can be filled by pipe X in 2 hrs and pipe Y in 6 hrs. At 10 am pipe X was opened. At what time will the tank  will the tank be filled if pipe Y is opened at 11 am?
1.  11. 45am
2.  11. 50am
3.  12. 45 am
4.  5 PM



10. 2 pipes A and B can fill a tank in 30 mins and 45 mins respectively. The pipe C can empty tank in 36 minutes. First A and B are opened. After 12 minutes C is opened.  Tank will be filled in how much total time (in mins)?
1.  12
2.  24
3.  42
4.  36


11. If 1 man or 2 women or 3 boys can complete a work in 44 days.  Find in how many days 1 man,1 woman and 1 boy will complete the work?
1.  48
2.  24
3.  12
4.  16


12.  A sum of money is sufficient to pay Oliver’s wages for 21 days and Tom’s wages for 28 days.  The sum of money will be sufficient to pay both’s wages for ______ days?
1.  16
2.  24
3.  28
4.  12


13.  Harri, Cait and Barry can complete a work individually in 16, 12 4/5 and 32 days respectively.  All of them started to work together but Harri leaves after 4 days, Cait leaves 3 days prior to the completion of the work.  In how many days was the work completed?
1.  18
2.  9
3.  45
4.  None


14. 3 pipes A,B and C can fill a cistern in 6 hours.  After 2 hours C pipe is closed. Then, A and B fill the cistern in 8 hours.  Find in how many hours C can alone fill the cistern .
1.  24
2.  12
3.  48
4.  50


15. Walking ¾ of his speed Thea is 10 minutes late for her office.  Find the usual time (in minutes) taken by her to reach office?
1.  40
2.  15
3.  10
4.  30